By Lloyd Snyder, P.E. | 02/15/2008
In today's regulatory environment, pipe fitters must understand the sanitary requirements placed on owners and install systems that can be sanitized in a fast, efficient and safe manner. An owner cannot afford the cost or time to train contractors on industry standards. Experienced engineering firms can provide guidance in contractor selection.
Construction manager selection is another overlooked art. The challenge is to find experienced road warriors who manage modern construction projects under strict performance requirements, tight costs and accelerated schedules.
The tasks that these experts must perform include:
Lastly, field engineering often is not considered in engineering firm selection. Over the lifespan of a project, people, products and process requirements will change, and that results in the need for field engineering. These changes often occur once equipment starts to be installed in the field, requiring quick, responsive, accurate design changes.
If an inexperienced engineering design firm does not understand these needs, they will often limit support during installation and have a difficulty supplying the necessary engineering resources. Field engineers also perform submittal reviews, installation acceptance reviews and commissioning preparation.
Commissioning considers every factor that determines how and when line equipment will begin functioning. To manage the process, the owner should craft and follow a comprehensive commissioning plan. A well developed, organized plan will enable a new manufacturing operation to come on-line sooner, reduce downtime and provide quicker returns.
Some of the key plan components include:
The final stage in commissioning is the performance acceptance test. These critical tests are often developed with each equipment supplier during the equipment procurement phase and are the contractual basis for equipment acceptance by the owner.
The tests need to be scheduled and executed with each major equipment supplier.
The commissioning plan documents the test protocol and the required results, whether they are operational or maintenance, and the approved follow up proocess to correct deficiencies
A successful manufacturing line launch requires the development of a methodical design, implementation and commissioning plan. This is often developed as a team effort among the owner, equipment suppliers and an engineering group.
The selected project execution method deployed, whether it is turnkey, DBB or a hybrid, determines the source of the engineers and specialists that will execute the plan.
Lloyd Snyder, P.E., is vice president-food & beverage at Woodard & Curran (www.woodardcurran.com), an integrated engineering, science and operations company. The firm has been serving food and beverage clients for more than 25 years. Contact Lloyd Snyder at 800-426-4262.